Instrumentation and Control System Upgrade - Electrical Installation at Wivenhoe Power Station
Wivenhoe Power Station - upgrade the control systems for its two 250 MW generating/pumping Units and associated Common Plant
Supply and installation of new or replacement control cabling shall be required as part of this project but existing cabling will be reused wherever possible. It is expected that some re-termination of existing cables shall be required to provide standard interfaces to field devices and to facilitate the addition of new field devices into the control systems.
Mandatory site inspection Friday 9 December 2011 at 9.30 am. PPE must be worn.
13 Jan, 2012
Power Generation and Distribution Machinery and Accessories - (100%)
open offer process
No
$1
(Estimate)
South East Queensland
2 Apr, 2012
20 Apr, 2012
8
None
Contractors
O'Donnell Griffin
34 Corporate Drive, Cannon Hill 4170, QLD, Australia, 4170