Supply & Deliver road paving materials and screenings.
REQUIREMENTS & TIMING
Type 2.3 CTB (2% cement) 1250 tonne – May-June 2016
CBR 15 material – 750 tonne – May-June 2016
Rock 150-200mm – 1500 tonne – May 2016
10mm Pre-coated screenings – 50 tonne – June 2016
Backfill Material – 500 tonne
Note: All granular products will be required to be delivered direct on road whereas the rock and screenings will be delivered into stockpile.
Project Specification
General
All work associated with the Offer shall be performed in accordance with the Department’s Technical Standard MRTS05 (07/15) – Unbound Pavements and MRTS22 (01/15) – Cover Aggregate. A copy of this specification is available from www.tmr.qld.gov.au or by contacting the project manager.