Primer Seal:
- Cart, heat and spray 16500 litres C170
- Supply and incorporate 3 parts cutter
- Hire of spreader truck approximately 50 hours
- 2 visits – July & August 2016
Second coat seal:
- Cart, heat and spray 28000 litres C170 at 1.70l/m2
- Load, haul and spread 14mm stone - 185m3 of 14mm screenings at 1m3/90m2
- Traffic Management (including placement of TRPM’s)
(14mm pre-coated screenings to be supplied by RoadTek)
All work to be in accordance with current TMR Standard Specifications
Primer seal – 2 visits July & August 2016
Second Coat Seal – October 2016
|