Supply & Deliver road paving materials and screenings.
REQUIREMENTS & TIMING
Location: 30km south of Ban Ban Springs
Type 2.1 – 10,000 tonnes - September to December 2017
Type 2.3 – 12,000 tonnes - September to December 2017
CBR 15 Material – 2,000 tonnes – September to October 2017
14mm Pre-coated screenings – 450 tonnes – February 2018
10mm Pre-coated screenings – 350 tonnes – September 2017
Rock – maximum 150mm – 250 tonnes (provisional quantity)
Bedding sand – 250 tonne – August 2017
Backfill material – 2,000 tonne – August 2017
Note: All granular products in general will be required to be delivered direct on road. All the screenings, bedding sand and backfill material will be delivered into stockpile.
The rate of delivery for Type 2.1 and 2.3 material is envisaged to be in the 1,000 tonne/day range per site.
Offerors are requested to supply an over and above rate for cartage in side tippers.
|