Location: Durong and 0-5km north of Durong
Type 2.1 – 25,500 tonnes - February to September 2018
Type 2.3 – 43,250 tonnes – February to September 2018
Type 2.5 – 2,500 tonnes – February - September 2018
14mm Pre-coated screenings – 950 tonnes – June- October 2018
10mm Pre-coated screenings – 760 tonnes – March - September 2018
Note: All screenings will be delivered into stockpile. It is envisaged that the majority of the paving material can be delivered directly onto the road, with only a small proportion being stockpiled.
The rate of delivery for Type 2.1 and 2.3 material is envisaged to be in the 1,000 tonne/day range.
|