Yerra Road Intersection Upgrade
Project duration May 2018 – August 2018
Type 2.1 - 4500 tonnes
Type 2.3 – 3100 tonnes
CBR15 – 250 tonnes (provisional quantity)
10mm Pre-coated Screenings – 125 Tonnes
14mm Pre-coated Screenings – 175 Tonnes
Note: All screenings will be delivered into stockpile. It is envisaged that the majority of the paving material can be delivered directly onto the road, with only a small proportion being stockpiled.
The rate of delivery for Type 2.1 material is envisaged to be in the 750-1000 tonne/day range.
General
All work associated with the Offer shall be performed in accordance with the Department’s Technical Standard
MRS05 (10/16) – Unbound Pavements
MRS22 (10/16) – Cover Aggregate.
MRS50 (10/16) – Specific Quality System Requirements
|