RoadTek are required to undertake bridge rehabilitation works on the Bowen Road Bridge, Townsville, from chainage Ch: 5.766 to Ch: 5.999km as shown in the locality plan. The project includes rehabilitation of 224 concrete piles and 16 pile caps of the bridge. As part of the works RoadTek are required to construct a suitable bund that will allow the works to be undertaken in separate stages. The bund is to be suitable to maintain access and protect the works through all tides, the bund will be constructed utilising sheet piling, or an earth wall or a combination of both. After the bunds are installed a dewatering system is required to be installed and in operation to allows works to be undertaken on the bridge piles. The dewatering system is to be installed, operated and removed as per the design specifications in the tender documents