View Contract Details

Andrew N. Liveris Building Project - Early Works Contract  

The University of Queensland
St Lucia, QLD, Australia, 4072
UQ1802EW
Andrew N. Liveris Building Project - Early Works Contract (UQ1802EW)
Works
Andrew N. Liveris Building Project - Early Works Contract

The scope of works for this Design & Construct contract being the “Early Works” (Early Works Project) is as follows:

  • Removal of HAZMAT from site
  • Relocate existing in ground services
  • Demolition of existing Frank White Building and Annex
  • Installation of a new mains gas from Cooper Road to Staff House Road
  • Installation and connection of the new storm water and sewer including diversion
  • Installation of below ground services conduits
  • Installation and connection of a new fire main
  • Installation of piles for the retiming wall – including shotcrete face and piling caps and associated works
  • Installation of piles under the lift core (excluding pile caps)
  • Relocate the existing Hawken water meter and Pentice water meter
  • Co-ordination of UQ contractor to install the new campus gas mains
  • Maintenance of the fire egress routes from / to the adjacent Prentice Building and Mansergh Shaw Building for the duration of the project
11 Jun, 2018
Building and Construction and Maintenance Services - (100%)
limited offer process
No
$4,786,669 (Fixed Price)
South East Queensland
29 Jun, 2018
3
Ashleigh Ferguson (DISABLED )
OFFICE: (07) 3365 1046

Contractors

McNab Constructions Australia Pty Ltd
12 Neil Street, Toowoomba, QLD, Australia, 4350
Price: $ 0.00