Seqwater requires the services of a qualified Consultant to develop a preliminary design, cost
estimation and tender documentation for the Kimberley Park – Pipe Modifications Project.
The initial contract is for Phases 1 and 2 with optional phases to be awareded at the discretion of Seqwater.
Phase 1 - Review and accept concept at the Kimberley Park Reservoir Complex;
Phase 2 - Develop the preliminary design and cost estimate for the business case;
Optional phases to be awareded at the discretion of Seqwater
Phase 3 - Prepare final design deliverables
Phase 4 - Prepare tender documentation including scope of work and pricing schedules
Phase 5 - Construction Support